Grace Yokley Middle School Addition Mountain View School District

This District challenged WLC to build school additions for an average of
$160.00/s.f. total project cost for two-story buildings and a gymnasium, including known site work improvements.

About Project

Part of the strategy was to simplify materials of the superstructure to shorten construction time frames to help save construction costs. WLC simplified the school’s exterior design to achieve a similar look of the existing school and followed every design decision with costs.

  • Estimated Cost$7.5 Million
  • Construction Cost: $7.8 Million
  • Square Footage:48,000
  • Cost/Square Foot:$162
  • Construction Duration:10 Months
  • Completion Date:August 2004
  • Principal:Paul Bonaccorsi
  • Senior Project Manager:Jeff Miller
  • Superintendent:Mike Powell
  • Delivery Method:CM/Multi-Prime

Education & Civic Construction Supervision

Leading the way in Construction Management

WLC Corporate Headquarters WLC Architects, Inc. / California Professional Management, Inc.

ALFC Classroom Building Addition Abundant Living Family Church

Door Components Manufacturing Headquarters – Door Components, Inc.